A footing is a trench filled with concrete. Enter the trench width and depth with the run length — or the number of pads — and the calculator returns yards and bags.
Slabs are 4 in; footings and pads 8–12 in.
Affiliate link. The price above is calculated from the unit price you entered — it is not a quote.
A 40 ft strip footing 16 inches wide and 10 inches deep contains 44.2 cubic feet of concrete — 48.8 cubic feet with a 10% allowance, or 1.81 cubic yards. That is about 3.7 tons, or 109 bags of 60 lb mix.
What the calculator assumes
- Width is the trench width at the bottom, not the width at grade. Trenches with sloped sides hold more concrete than the bottom dimension suggests.
- Depth is the concrete thickness, measured from the bottom of the trench to the top of the footing — not to the top of the wall it carries.
- How many multiplies the whole volume, so one entry covers a run of identical pads.
- Waste defaults to 10%. Footings are dug by machine and rarely uniform: a trench that wanders 2 inches wide over 40 ft is another 0.2 cubic yards.
Strip versus pad footings
| Type | Carries | Typical size | Volume per unit |
|---|---|---|---|
| Strip footing | Foundation wall, brick | 16 in × 10 in | 0.41 cu ft per linear ft |
| Pad footing | Deck post, column | 18 in × 18 in × 12 in | 2.25 cu ft |
| Deck pier | 6 × 6 post | 12 in diameter × 36 in | 0.79 cu ft |
| Grade beam | Load between piers | 12 in × 18 in | 1.5 cu ft per linear ft |
Set “how many” to the number of identical pads and enter one pad’s dimensions. That is the whole trick to pricing a deck’s footings: measure once, count, multiply.
Ordering concrete for footings
Most footing jobs land between 1 and 4 cubic yards, which is the awkward zone: too much for bags, small enough to attract a short-load fee from a ready-mix supplier. Two ways out:
- Order the whole job at once and pour all the footings in a single morning, so one truck covers it.
- Mix on site if the total is under a yard. Sixty bags is a long day with a wheelbarrow mixer but avoids the fee.
Check the short-load charge before deciding. On a 2 yard order it can be 30% of the bill.
Where the number goes wrong
Forgetting the pier above the footing. A footing and the wall it supports are separate pours. The footing volume stops at the top of the footing.
Not allowing for the bell. If the base is undercut wider than the trench — a bell footing — the volume is larger than a straight prism. Measure the widest part.
Digging into rain. An open trench that fills with water needs the water and the slurry removed before the pour, or the concrete is diluted at the base. That is a schedule problem the calculator cannot fix, but ordering a little extra covers the over-excavation.
Concrete mix: quick conversions
A yard of mixed concrete weighs just over 2 tons, about 50% more than a yard of gravel, because cement paste and water fill the voids stone leaves. At 0.45 cu ft per bag it takes 60 bags to make that yard.
| Quantity | Equivalent |
|---|---|
| 1 cubic yard | 2.02 tons · 4,050 lb |
| 1 ton | 0.49 cu yd · 13.3 cu ft |
| 1 cubic yard, 4 in deep | 81 sq ft |
| 1 ton, 4 in deep | 40 sq ft |
| Bags per cubic yard (0.45 cu ft) | 60 bags |
Every figure is derived from the 150 lb/ft³ density this site uses for concrete mix. Area scales inversely with depth, so at 8 in a cubic yard covers half the area it does at 4 in. Density table and the full formula →
Concrete mix questions
How wide and deep should a footing be?
Twelve to sixteen inches wide and 8–12 inches deep is typical for a single-storey addition on good soil. That is a starting point, not a specification — footing size follows the load and the soil, and a footing under a structural wall needs an engineer.
How do I calculate concrete for a strip footing?
Length in feet × width in feet × depth in feet ÷ 27. A 40 ft run at 16 inches wide and 10 inches deep is 40 × 1.33 × 0.83 = 44 cubic feet, which is 1.6 cubic yards before the waste allowance.
How many bags of concrete for a footing?
About 109 sixty-pound bags for the 1.8 yard example above. Most people order ready-mix past about 1 cubic yard — 109 bags is over three tons to carry and mix by hand.
Does a footing need rebar?
Two continuous #4 bars is the usual minimum for a residential strip footing, on 3 inch chairs so they sit in the lower third. Unreinforced footings work until the soil moves, and then they crack through.