Round forms are cylinders, so the volume follows from diameter and height. Enter the tube size, the pour height and how many you have.
Footing depth is set by the frost line, not the load — 12 in in the deep south, 48 in or more in the north.
Affiliate link. The price above is calculated from the unit price you entered — it is not a quote.
Six 12 inch tubes filled 4 ft high hold 18.9 cubic feet of concrete — 20.7 cubic feet with a 10% allowance, or 0.77 cubic yards. That is 47 bags of 60 lb mix, or 1.5 tons.
What the calculator assumes
- Diameter is entered in feet because the field is a length. An 8 in tube is 0.67, a 10 in is 0.83, a 12 in is 1.0.
- Height is entered in inches. Round forms are usually filled to a level above the finished grade, so enter the actual pour height rather than the tube length.
- How many multiplies the volume across identical tubes.
- Waste defaults to 10%. Concrete shrinks into the tube and the first shovelful always misses; on a 6 tube job, 10% is one extra tube’s worth.
Volume per tube
| Tube | Area | Concrete per foot | 4 ft tube |
|---|---|---|---|
| 8 in | 0.35 sq ft | 0.35 cu ft | 1.4 cu ft |
| 10 in | 0.55 sq ft | 0.55 cu ft | 2.2 cu ft |
| 12 in | 0.79 sq ft | 0.79 cu ft | 3.1 cu ft |
| 16 in | 1.40 sq ft | 1.40 cu ft | 5.6 cu ft |
| 24 in | 3.14 sq ft | 3.14 cu ft | 12.6 cu ft |
The jump from 12 to 16 inches is nearly double the concrete, which is why deck plans specify the smallest tube that satisfies the load and the frost depth.
Setting tubes properly
The concrete is the easy part. Three things decide whether the post stays put:
- Hole diameter is 2–3× the tube diameter, so an 12 in tube goes in a 24–30 in hole.
- Base is 6 inches of compacted gravel, so the tube is not sitting in mud.
- Flare the base — a tube that is wider at the bottom resists uplift, which matters on decks and fence lines.
Fill the tube in lifts of about 2 ft and rod each lift to remove air pockets. A tube filled in one pour from the top can bridge and leave a void that only shows up as a cracked pier a year later.
Where the number goes wrong
Pouring to the top of the tube. The tube is usually left 2–4 inches proud of grade and then cut down. Concrete to the top of a 48 inch tube in a 42 inch hole is wasted.
Mixing in a wheelbarrow. A 12 in × 4 ft tube is 3 cubic feet, which is seven bags — more than most people want to mix by hand, six times over.
Forgetting the anchors. Post bases and anchor bolts need to be set in the wet concrete within the working window. That is not a volume question, but it is the reason a pour cannot be paused.
Concrete mix questions
How many bags of concrete for a 12 inch sonotube?
About 8 bags of 60 lb mix per foot of height. A 12 inch tube holds 0.785 cubic feet per foot, and a 60 lb bag yields 0.45 cubic feet. A 4 ft tube is 3.1 cubic feet, or 7 bags before waste.
How do I enter the diameter in feet?
Divide inches by 12: an 8 inch tube is 0.67 ft, 10 inch is 0.83 ft, 12 inch is 1 ft. The height field stays in inches, which is why the two fields carry different units.
How deep do deck post footings need to be?
Below the frost line, which is 12 inches in the deep south and 48 inches or more in northern states. Frost depth governs, not the load — a footing that heaves takes the deck with it.
Should the tube be left in the ground?
Yes. Sonotube is a form, not a structural element, but it stays in place: it keeps the concrete from contacting soil and stops the hole collapsing. Cut it off at the finished grade line while the concrete is still green.